Council is constructing a new splash park and waterslides at Maribyrnong Aquatic Centre (MAC), which will include the installation of:
Due to the liquidation of the contractor in September 2023, construction works have been temporarily ceased at the Maribyrnong Aquatic Centre.
A thorough review and redesign of the structural elements has been completed, complemented by comprehensive structural and civil site surveys to provide up-to-date condition reports. This groundwork is crucial for the next phase of the project.
Council is now preparing to initiate the tender process, with the goal of appointing a new contractor and obtaining an amended building permit to re-commence construction at the earliest opportunity to complete the remainder of the works.
An updated timeline for the project will be shared upon the appointment of a new contractor.
We extend our gratitude to the community for your patience as we navigate these challenges to deliver a space that can be enjoyed by all.
The Maribyrnong Aquatic Centre Splash Park and Waterslides project is jointly funded by the Victorian State Government.
Check out a video animation of the new Splash Park and Waterslides below:
1 Aquatic Drive, Maribyrnong 3032 View Map
1 Aquatic Drive , Maribyrnong 3032
Render of the exterior of MAC with the new Splash Park and Waterslides
MAC Splash Park progress update May 2023
MAC Splash Park slide components delivered May 2023